Landscape Plus completed Stage 1 of West Side Place for Far East Consortium in December 2022.

The project duration was just over two years; significantly delayed after the builder collapsed. Fortunately, Landscape Plus was able to work for the developer to complete the contracted works.

Landscape Plus delivered civil and landscaping works to the perimeter of the building, paving to the central laneway, and landscaping to levels 7 and 11. The landscaping component included the installation of steel planters, stone paving and mature trees across multiple levels all the way up to the 64th floor.

Back to project list

West Side Place

client Far East Consortium
value $4,200,000